The way is cleared for a 150 MW DC solar power plant of Solar Energy Group Europe as the company entered a transmission connection agreement with Kosovo’s transmission system operator KOSTT recently (in the picture). (Photo Credit: KOSTT Sh.A.)
Key Takeaways
- Kosovo’s KOSTT has agreed for transmission connection for a 150 MW DC solar power project in the country
- Solar Energy Group Europe plans to set it up in Gjakova municipality and will be connected to the grid by 2022
- The project will have an alternate current capacity of 136 MW AC, according to KOSTT
Related Articles
-
192 MW Solar Park Planned To Come Up In Kosovo
Kosovo To Host 2 Solar PV Projects With 96 MW Capacity Each Under Transmission Connection Agreement Between KOSTT & Dukagjini Solar
(18. March 2021)
-
RE Auction Guidelines By EBRD & EnCS
New Policy Guidelines For Renewable Energy Auctions Issued By EBRD & EnCS To Ensure Transparency & Accountability in European Member Countries
(30. March 2018)
-
Kosovo To Launch PV Auctions
PV Auctions To See Light Of The Day In European Country Kosovo With An Expected Investment Of Around €100 million ($116 million)
(07. November 2017)
A 150 MW DC/136 MW AC solar power project is being planned in Kosovo, announced the country’s transmission system operator KOSTT on its website. It entered an agreement to allow the project’s connection to its transmission system with the Director of the Solar Energy Group Europe, Egbert Schnuse. This would basically double the total installed solar capacity of the Eastern European country.
The brief statement from KOSTT reveals the planned project will be located in the municipality of Gjakova and connected to the 110 kV transmission network through the new 110 kV line with a length of about 6.5 km.
Solar Energy Group Europe plans to start commercial operations for the plant in 2022.
In December 2020, the State Aid Commission expressed its disapproval for the feed-in-tariff (FIT) tariffs approved by Kosovo Energy Regulatory Office for 20 MW solar capacity, calling it incompliant with European Union rules (see Kosovo’s FIT For 20 MW Solar PV Projects ‘Incompliant’).
At the end of 2019, Kosovo’s total installed renewable energy capacity was 140 MW, according to the International Renewable Energy Agency (IRENA) with solar PV’s share being 9 MW.
The Balkan country has also been wanting to launch an auction system for renewable energy as the European Bank for Reconstruction and Development (EBRD) was looking for a consultant to help design the scheme in September 2019. The bank back then said Kosovo’s Energy Strategy shows the country wants to have 400 MW of renewables in its total energy mix by 2026 (see EBRD Seeking Consultant For Kosovo RE Auction).