Taking cognizance of the problems faced by power generating companies in ensuring timely implementation of a 'pass-through' option for their projects, the Indian Ministry of Power has issued instructions to quicken the process.
In a letter addressed to the Central Electricity Regulatory Commission (CERC), the ministry has acknowledged the problems faced by generating companies. It reads, "The difficulty is mainly because of considerable time being consumed in the approval process resulting into severe cash flow problems to the generating companies. This has also resulted in stress in the power sector."
It has clarified the following points in its letter:
These measures, according to the ministry, will ensure sustainability of the electricity market in the larger public interest, and also address the issue.
Background
Indian solar power project developers had been worried when the government started investigating q safeguard duty petition against imported solar cells at the behest of domestic solar products manufacturers (see ISMA Calls For Safeguard Duty On Imported Cells). It then brought in a 'pass through option' to relieve the fears of developers that would allow them to pass through any change in law that occurs after the award of bids.
However, such measures have done little to cheer up the developer community that sees several years of legal fight to avail the provision. Mercom India Research lauds the initiative, yet says more clarity is needed to set the process and its timely implementation.
Meanwhile, the Orissa High Court will take up the case against safeguard duty imposition for the next hearing scheduled for September 19, 2018. The high court had put a temporary stay on it (see Court Pauses India's Safeguard Duty).