Solar modules required for GIPCL tender must have a minimum power rating of 540 W. (Illustrative Photo; Photo Credit: photoschmidt/Shutterstock.com) 
Tenders

Gujarat Company Seeking 625 MW DC Solar Module Capacity

GIPCL Issues Call For Panels For Project Deployment In Great Rann Of Kutch

Anu Bhambhani

  • GIPCL is looking for solar module supply for a 500 MW AC solar power plant  

  • The project is located near village Khavda in the Great Rann of Kutch in Gujarat  

  • It is part of the 2.375 GW Ultra Mega Hybrid Renewables Project of the company  

State-owned power generation company Gujarat Industries Power Company Limited (GIPCL) has launched a call for the supply of 625 MW DC/500 MW AC solar PV modules for a solar project it is developing in the Great Rann of Kutch, Gujarat.  

This project is part of a 2.375 GW Ultra Mega Solar/Wind/Hybrid Renewable Energy Park being established near village Khavda.  

GIPCL said the scope of this tender is to procure the solar modules and deliver the same to the balance of system (BoS) contractor for installation.  

Solar panels under the tender are required to use bifacial technology with a minimum power rating of 540 W and a maximum of 570 W.  

Module delivery needs to be attempted in 6 lots between March 2025 and October 2025, with the largest chunk of 250 MW DC to be delivered in September 2025.   

It specifies that the modules to be delivered must be listed in the Ministry of New and Renewable Energy’s Approved List of Models and Manufacturers (ALMM) list.  

The tender for this requirement was launched on August 21, 2024. The last date to submit the offers is September 25, 2024, as per details available on GIPCL’s website 

In September 2023, GIPCL invited bids for the supply of 750 MW DC/600 MW AC solar modules for its Khavda project (see Solar Module Supply Tender For 600 MW AC Project).