Statkraft Signs Battery Tolling Deal With Zelestra In Italy

The 175 MW / 700 MWh, 4-hour storage project in Central Italy will be built and operated by Zelestra and will be operational in 2028
The 8-year physical tolling agreement covers the entire capacity of Zelestra’s 175 MW / 700 MWh, 4-hour BESS, to be connected to an existing Terna substation in Central Italy.
The 8-year physical tolling agreement covers the entire capacity of Zelestra’s 175 MW / 700 MWh, 4-hour BESS, to be connected to an existing Terna substation in Central Italy. Image Credit: Zelestra
Published on: 
Key Takeaways
  • Zelestra will build and operate the project, while Statkraft will optimize its revenues across all relevant markets

  • Italy will need around 50 GWh of new utility-scale storage to integrate growing renewables, according to Terna's PNIEC 2030 scenario

  • Bilateral tolling can complement Italy's regulated storage procurement, giving investment-ready projects long-term revenue visibility

Key Takeaways

Global renewable energy company Zelestra announced it has signed an 8-year physical tolling agreement with Statkraft, one of Europe's largest renewable energy producers, for a storage project in Italy. The agreement covers the entire capacity of Zelestra's 175 MW / 700 MWh, 4-hour BESS, which will be connected to an existing Terna substation in Central Italy. 

The fully authorized facility will be operational in 2028. It will be Zelestra's first storage project in Central Italy. While Zelestra will build and operate the project, Statkraft will use its market access and battery optimization expertise to maximize the facility's revenues across all relevant markets. 

It is Statkraft's first tolling agreement in Southern Europe and Zelestra's fourth in Italy. The agreement takes Zelestra to 5.4 GWh of contracted BESS worldwide, including 3.5 GWh in Italy. 

Italy Needs Around 50 GWh Of New Storage

According to the PNIEC 2030 scenario developed by Terna, the Italian power system will need around 50 GWh of new utility-scale storage capacity to integrate growing renewable generation.

The agreement illustrates the complementary role that bilateral tolling arrangements can play alongside Italy's regulated storage procurement framework, providing long-term revenue visibility for investment-ready projects with grid connections.

The structure strengthens Statkraft's presence in the Italian energy market. It supports a project expected to contribute to system flexibility, renewable energy integration, and security of supply from 2028.

Speaking about the agreement, Simon Kornek, Vice President South European Origination, Statkraft, said, "Our first tolling agreement in Southern Europe demonstrates how long-term commercial partnerships can help make large-scale battery projects investable. Zelestra brings a strong, investment-ready project, while Statkraft brings market access, optimisation capability and experience across European power markets. Together, we can unlock the flexibility that the Italian power system increasingly needs. This is the role we want to play as a market integrator."

The agreement builds on Statkraft's battery optimization business, launched in the UK in 2018. The business now covers more than 4 GW of contracted BESS capacity across nine European countries, as the company expands its flexibility business in Southern Europe.

Echoing similar sentiments, Eliano Russo, CEO of Zelestra Italy, said: "We are proud to collaborate with Statkraft on this project. Their expertise in market access and storage asset optimisation is precisely what the facility needs to make the most of its capacity. Zelestra now has 5.4 GWh of batteries under contract, 3.5 GWh of them in Italy across four projects, which puts us firmly among the global leaders in storage."

Italy is one of Zelestra's fastest-growing markets. The company has a portfolio of more than 2 GW of solar and BESS projects there.