Chinese perovskite PV manufacturer UtmoLight has announced that a 2.81 m² single-junction perovskite module developed in collaboration with the University of New South Wales (UNSW) achieved a stabilized conversion efficiency of 19.6% under maximum power point tracking (MPPT), based on testing by Fraunhofer ISE. UtmoLight said the result sets a world record for large-area perovskite modules, with efficiency fluctuations kept within ±0.1% during a continuous 300-second stabilized output test.
The partners previously achieved 23.5% efficiency on a 30 × 30 cm perovskite module. UtmoLight said the latest result shows the potential to scale up and replicate the technology in mass manufacturing. Since producing its first 2.81 m² module on a GW-scale production line in late 2024, the company says it has integrated R&D advances into its manufacturing processes, raising the reported efficiency of this module format from 17.44% to 19.6%.
Last month, UNSW and UtmoLight report a certified stabilized efficiency of 23.5% for a perovskite submodule (see Perovskite Submodule Efficiency Record).
China Southern Power Grid Energy Storage Co., Ltd. (CSGES) has started on-site grid-connection testing and commissioning for its 100 MW/400 MWh battery storage project and associated grid facilities at Huaping Industrial Park in Lijiang, Yunnan Province. Developed by a CSGES subsidiary, the 4-hour facility uses vanadium redox flow batteries and includes a new prefabricated 220 kV step-up substation and roughly 10 km of 220 kV transmission lines. The developer describes it as Yunnan’s first grid-forming vanadium flow shared energy storage project, with operations targeted to begin by the end of 2026.
Combining vanadium flow battery technology, grid-forming capabilities, and a shared-storage business model, the facility is designed to offer capacity-leasing arrangements totaling up to three times its installed capacity, according to the project manager. It is also expected to support grid stability in Lijiang, where renewable energy penetration is rising, and the local grid has limited voltage and frequency support capabilities.
China’s Ningxia Hui Autonomous Region has released its 15th Five-Year Plan (2026-2030) for developing a new-type energy system, projecting total installed power generation capacity of 142 GW by 2030, up 55.7% from 2025. Energy storage capacity is targeted to climb from 7.63 GW to 30 GW, while the share of non-fossil fuels in electricity generation is expected to rise from 32% to 43%.
The plan calls for building three 10 GW-class renewable energy bases in Yanchi, Lingwu, and Shapotou, alongside several GW-scale bases. It also backs distributed PV deployment, building-integrated PV (BIPV) pilot projects, coordinated wind-solar-storage operation, and grid-forming technologies to improve the firm output of wind and solar power.
On energy storage, the plan calls for developing grid-side shared storage, grid-forming storage, and shared storage facilities in industrial parks. It also supports pumped hydro, compressed-air, flow battery, and flywheel storage, while seeking to refine capacity pricing for new-type storage and gradually transition toward a reliable capacity compensation mechanism.
Earlier this month, Ningxia-based renewable energy developer Ningxia Guoyun New Energy announced it had completed major equipment installation, commissioning, and grid connection at two independent energy storage plants (see China Solar PV News Snippets).
Jilin Province has launched a mechanism price auction for incremental wind and solar projects for 2027, covering an annual mechanism electricity volume of 9.322 TWh, comprising 8.2 TWh of wind power and 1.122 TWh of solar power. Eligible projects must achieve full-capacity grid connection between June 1, 2025, and December 31, 2027, and must not have already been included in the mechanism or disqualified from bidding.
The bidding ceiling for both solar and wind is RMB 326.6/MWh, with a floor of RMB 170/MWh. The mechanism price will apply for 12 years, and individual projects may bid for up to 60% of their estimated annual grid-fed electricity.
In April, Jilin announced a target of 70 GW of combined wind and solar capacity by 2030 as part of its 15th Five-Year Plan (2026-2030) (see China Solar PV News Snippets).