India Curtails 1.46 Billion Units Of Solar Power In 2 Months

Solar generation grew 39% YoY in Q2 FY2026–27, but limited operational battery storage and grid constraints contributed to renewable energy curtailment, says CREA
CREA
India’s cumulative installed renewable energy capacity, excluding large hydro, expanded to 243 GW in August 2026, driven by solar’s 168 GW. Yet, solar energy generation experiences curtailment because of grid and operational constraints.(Image Credit: CREA)
Published on: 
Key Takeaways
  • CREA says solar accounted for 58% of the increase in renewable electricity generation during Q2 FY 2026-27 

  • It reached a daily record of 705 million units on September 30, 2026, yet India curtailed 1,462 million units of solar electricity in July and August, despite high power demand 

  • Insufficient battery storage capacity is also a challenge, with 9.1 GWh operational against 151 GWh of tendered battery storage projects as of August 2026 

India’s solar power generation grew 39% year-on-year (YoY) in Q2 FY2026–27. However, grid and operational constraints, along with limited energy storage capacity, led to the curtailment of 1.46 billion units of solar electricity in July and August, despite high electricity demand, according to a report by the Center for Research on Energy and Clean Air (CREA). 

India’s peak electricity demand reached 270 GW on July 16, 2026, up 18% from 230 GW in the same quarter a year earlier. Daily peak demand occurred during solar-generation hours on 62 of the quarter’s 92 days. 

Despite record peak demand, India’s coal power plants operated at a 68% utilization rate in Q2 FY2026–27, according to CREA. 

However, although solar was the fastest-growing major source of electricity generation during the quarter, with output reaching a record 705 million units (MU) on September 30, 2026, it was curtailed. This renewable energy source accounted for 58% of the increase in renewable electricity generation during the quarter.   

Nevertheless, India’s solar capacity reached 168 GW as of August 2026, accounting for around 30% of the country’s total installed power capacity of 555 GW, next only to coal and lignite’s 231 GW. The latter accounted for 66% of the national generation mix even as plant-level stocks declined. 

During the reporting quarter, in the months of July and August, India curtailed 1,462 MU of solar and 373 MU of wind capacity, out of 1,835 MU of renewable energy capacity curtailed. 

In light of these findings, Manoj Kumar, India Analyst at CREA, argues that India must assess new thermal capacity against expected demand, renewable generation, and storage availability, as solar increasingly meets daytime electricity demand while storage helps meet evening and nighttime peaks. 

“This will help avoid building capacity that could remain underutilised as India’s power system evolves,” added Kumar. 

According to CREA’s report, titled Quarterly Energy Snapshot for India: Q2 2026–27, India had approximately 9.1 GWh of operational battery energy storage system (BESS) capacity as of the time of the report’s publication. Another 3 GWh is expected to be commissioned by December 2026. As of August 2026, storage projects totaling approximately 290 GWh had been tendered. This included 151 GWh of battery storage and 142 GWh of pumped hydro storage. 

Storage contributed up to 5.5 GW during nighttime peak demand, up from 4.1 GW in the first quarter of fiscal 2026-27. The gap between the storage project pipeline and operational capacity is quite visible, since storage met only about 1% to 2% of national electricity demand during these periods. 

In a recent report, Rubix Data Sciences said India will need up to INR 4.79 trillion in investment to meet its projected BESS requirement – 236.22 GWh by FY 2031-32 – as renewable capacity and peak power demand rise (see India BESS Demand Estimated To Reach 236 GWh By FY 2032).   