EU lawmakers have agreed to streamline permitting for renewable energy projects, electricity grids, and energy storage facilities
The measures agreed upon include single digital portals, time limits, and possible tacit approval for intermediate administrative steps
The agreement is the first part of the European Grids Package, which also includes a revision of the TEN-E Regulation
The European Union (EU) has agreed to fast-track permitting for renewable energy projects, introducing shorter approval deadlines for solar and energy storage facilities.
The deal sets a three-month limit for solar and co-located storage projects and raises the permit exemption threshold for small-scale installations from 100 kW to 200 kW.
The European Parliament and the Council of the EU reached a provisional agreement on November 18, 2026, on the permitting reform under the European Grids Package, a key deliverable of the One Europe, One Market roadmap. It will now require formal approval by the Council and the European Parliament, followed by legal-linguistic revision. Earlier, the Council had backed the European Grids Package proposed by the European Commission (see 22 EU Countries Back Up To 35 GW Energy Storage Push By 2028).
Once formally adopted, EU member states will have 18 months to incorporate the new provisions into national legislation.
What’s key here is that this agreement addresses a major concern for the European renewable energy industry: lengthy permitting processes that hold back the development of critical energy infrastructure across the bloc.
According to SolarPower Europe, solar projects face permitting delays of more than two years, sometimes up to four years, in several European countries. This, the association says, is double the maximum duration allowed under the Renewable Energy Directive (RED III) framework (see EU Member States Lag On RE Permitting Reforms).
The European Commission itself points out that electricity transmission grid projects currently take more than 10 years to implement, with over half of that time spent obtaining permits. It terms this as a major obstacle to the timely rollout of renewable energy in the bloc.
This should change under the provisional agreement reached. It agrees to accelerate permitting procedures for renewable energy and make them more transparent.
“Faster, streamlined permitting will help accelerate electrification in Europe. We need grid infrastructure for clean, affordable, and homegrown energy and to break our dependence on imported fossil fuels,” stressed Ireland’s Minister for Climate, Energy and the Environment, Darragh O’Brien.
Among the key points reached under the provisional agreement are:
Deadlines for the approval and grid connection for renewable energy projects and energy storage facilities, for instance, will be streamlined to eliminate unnecessary delays, says the Council.
Time limits will be introduced for permitting transmission and distribution grid projects, standalone energy storage and charging stations.
EU member states will be able to designate renewable energy and electricity grid projects as being of overriding public interest. This would help prioritize their development, although member states can retain discretion to protect security, defense and cultural heritage interests.
The agreement also allows member states to introduce tacit approval for certain intermediate administrative steps. Under this provision, a lack of response from authorities within the applicable timeframe may be treated as approval, helping prevent administrative bottlenecks.
Renewable energy developers will have access to fully digitalized permitting procedures through single or connected digital portals. These will give applicants a single point of access, making application submission and processing simpler and more transparent.
Permitting requirements for certain small-scale renewable energy projects will be removed, while accelerating the upgrading of existing installations.
Environmental assessments will be streamlined while maintaining nature protection safeguards.
The agreement also addresses public acceptance of renewable energy projects and calls for fair benefit-sharing with local communities hosting renewable energy projects with an installed capacity above 7 MW. This threshold has been lowered from 10 MW.
European Commissioner for Energy and Housing Dan Jørgensen said the agreement would accelerate the deployment of electricity grids, renewable energy projects and storage facilities. This would help lower energy costs, strengthen energy security and reduce Europe's dependence on imported fossil fuels, he said.
The provisional agreement forms the permitting component of the broader European Grids Package, proposed by the European Commission in December 2025. The package has two legislative components: the permitting directive and a revision of the Trans-European Networks for Energy (TEN-E) Regulation, which focuses on infrastructure planning, cross-border connections and the resilience of energy networks.