Spain Sets 80% Renewable Energy Rule For Data Centers

Spain's new decree requires data centers with grid access capacity of at least 10 MW to cover 80% of electricity consumption with renewable energy
Data Centers
Spain's decree requires data centers with grid access capacity of at least 10 MW to meet renewable energy and efficiency requirements.(Illustrative Image; Image Credit: on.u/Shutterstock.com)
Published on: 
Key Takeaways
  • Through a new Royal Decree, data centers with grid access capacity of at least 10 MW in Spain must cover 80% of their electricity consumption with renewable energy

  • Data centers participating in the Automatic Power Reduction System can follow a phased alternative renewable energy matching requirement for five years

  • The decree sets energy and water efficiency standards and requires data centers above 500 kW to report sustainability and energy performance information

Over two months after Spain proposed renewable energy consumption rules for new data centers above 1 MW, Spain has approved new sustainability requirements for large data centers. This includes a requirement to cover 80% of electricity consumption with renewable energy (see Spain Pushes For Hourly RE Consumption For Data Centers).   

Approved by the Council of Ministers, the Royal Decree 1032/2026 applies to data centers with grid access capacity of at least 10 MW.

Under the decree, data centers must demonstrate that at least 80% of their electricity consumption is covered by renewable energy, with hourly matching. The requirement will remain in place until renewable energy accounts for more than 90% of Spain's electricity mix.

The renewable energy requirement follows an additionality principle. Renewable generation used to meet the requirement must generally have been added to the electricity system no more than 36 months before the data center begins operating. The calculation can include self-consumption, energy storage and electricity supply contracts lasting more than six years. Solar PV installations, certain biomass plants and repowered facilities are subject to exceptions to the additionality timeframe.

For five years following the decree's approval, these facilities may meet a lower renewable energy requirement during peak periods. They must cover 60% of consumption with additional renewable energy during peak hours (P1) until December 31, 2028. The requirement will increase to 70% during peak and shoulder hours (P1 and P2) for the remainder of the five-year period.

Non-compliance with the time-of-use and additionality requirements will be penalized, and may lead to sanctions, including suspension of grid access and connection rights for up to three years. Data center projects will have six months to adapt to the requirements and prove compliance.

The rules aim to promote the orderly development of data centers while protecting the electricity system, limiting costs for consumers and supporting the country's energy and digital transition, according to the Ministry for Ecological Transition and the Demographic Challenge (MITECO).

The decree's hourly matching provision has drawn attention to how the 80% requirement will be interpreted and implemented. An analysis by EnergyTag and PyPSA Labs highlights a distinction between matching 80% of electricity consumption with renewable generation on an annual basis, using hourly data, and meeting the 80% threshold in every individual hour.

The analysis argues that requiring 80% renewable coverage in every hour could be significantly more demanding than conventional hourly matching over the year. It could require data centers to build or contract for a larger renewable energy and storage portfolio to cover periods of low wind and solar generation.

As per the Royal Decree, data centers must also comply with energy and water efficiency requirements based on European standards. Facilities with capacity above 500 kW must report energy efficiency and sustainability information to the Ministry for Ecological Transition and Demographic Challenge (MITECO), which will publish the information annually.

Data centers above 1 MW must also report whether, and how, they follow the latest European Code of Conduct on Energy Efficiency in Data Centres. The decree includes additional resilience and digital sovereignty requirements for data centers hosting high-security public information systems.

The government said the regulation is intended to prevent an uncontrolled expansion of data centers from increasing electricity costs for consumers.

Deputy Prime Minister and Minister for Ecological Transition Sara Aagesen said that, without the decree, electricity bills could face an impact of €5 billion, with industrial consumers potentially paying 25% more for electricity.