

Trina Storage launched its Elementa Hybrid Genset solution at RE+ 2026 in las Vegas
The genset integrates a 2.5 MW gas-based modular plant and 5/10 MW BESS with PCSs within a single platform
It supports two system configurations: double power conversion for electrical isolation from an unstable grid, and parallel load connection to sense rapid AI workload fluctuations
Trinasolar's energy storage arm, Trina Storage, launched its latest Elementa Hybrid Genset solution at RE+ 2026, targeting the energy demands of US AI data center (AIDC) developments.
This hybrid solution integrates a modular power plant with a 2.5 MW gas-based engine and the Elementa + Electra Cell-to-Grid battery energy storage system (BESS) on a single platform. The storage section has a reference configuration with 5/10 MW DC blocks with a power conversion system (PCS).
While the gas-based engine and turbine are supplied by external companies, Trinastorage acts as the system integrator. The gas-based plant supplies stable power to AI workloads (base load). The BESS, by contrast, comes into play during rapid AI workload fluctuations (which gas-based power plants struggle to handle) by quickly charging/discharging.
This platform also features a hybrid plant controller. It predicts any fast changes in AIDC power demand, which follow rapid BESS responses before any slow-response power source resumes operation. This is called load transient sensing, explains Trina Storage, while the controller's hybrid power coordination function activates the BESS to respond to sudden load spikes.
Meanwhile, the gas generator gradually ramps up before the demand stabilizes, facilitating a balance between the two power sources. The plant controller also features emergency backup support during fault occurrences. It isolates the faulty parts from the AIDC system and activates the BESS's grid-forming feature and available gas generators for fast backup support to critical loads, with a staggered power restoration across the site.
The Elementa Hybrid Genset supports two system configurations: double power conversion and parallel load, depending on AI workload profile and grid conditions. The former system places its BESS between two PCSs (gas generator- and AI-server side). The system switches from gas generators to the BESS and discharges to AIDC loads via the server-side PCS, while simultaneously charging from the grid source during rapid grid-side fluctuations.
According to Trina Storage, the dual conversion facilitates electrical isolation from the unstable grid source and provides quality power to AIDC. In comparison, the parallel load configuration senses AI workload fluctuations and prioritizes BESS sources over gas generators to deliver a cost-efficient and reliable power supply.
It validates the system (hybrid genset) design and performance through simulations and hardware-in-the-loop testing. In addition, testing and certifications for grid-forming and hybrid control strategies are ongoing.
Eric Cao, Vice President of Trina North American PV and BESS Business, said, "Elementa Hybrid Genset brings gas generation, battery storage and hybrid controls together in one system architecture, designed to coordinate these resources according to project needs." He added that this system addresses the demanding power requirements of AIDC, especially when workloads fluctuate rapidly or the grid is constrained.