The Bosnia and Herzegovina (BiH) Municipality of Tomislavgrad has invited bids to secure a piece of land in the region for the development of Orlovac Solar Power Plant having 102.5 MW DC/92.5 MW AC installed capacity.
The land is owned by the municipality and is located near Eminovo Selo village and will be provided to be used for the purpose for a period of 30 years. Solar power plant on completion will need to be connected to the grid via 110 kV, 220 kV and 400 kV transmission network issued by Elektroprijenos BiH Banja Luka.
Solar power plant will need to be commissioned within a period of 60 months from the date of contract being signed.
The call was launched on March 3, 2023 with last date to submit bids being March 21, 2023. Details are available on Tomislavgrad municipality's website.
Previously, West Herzegovina Canton Government also issued a call in November 2021 for interested bidders to win 30-year concession rights for the construction of a 25 MW solar power plant on land in Starka (see Tender For 25 MW Solar Power Plant In BIH).